AI use case

AI for construction schedule and progress tracking

AI construction progress tracking matches site photos to the schedule and BIM model to show what is actually built, for site teams and owners. The photos are captured with a hardhat mounted camera on regular site walks and compared with planned tasks and quantities, so teams see where trades are behind and where installed work does not match the design, without walking the site by hand.

By Len Debets · Last verified 29 September 2026 · 9 public deployments

70%
Median productivity gain, vendor reported
3 deployments.
10%
Reported error reduction
Layton Construction, vendor claim.
USD 103,500 to USD 1.6 million
Indicative value per year
A general contractor running 10 active projects averaging 40,000 square feet each. Worked example, see how it is calculated.

What problem does it solve?

A general contractor knows what should be built from the schedule and the BIM model, but not reliably what is actually built. The standard method is manual: a superintendent or project engineer walks the site, estimates the percentage complete of each trade by eye, and writes it up for the weekly meeting. That estimate is subjective, it takes site staff away from managing the work itself, and it usually surfaces a schedule slip or a quality issue only after it has already cost time to fix.

The effect compounds on a multi trade, multi floor project. Different superintendents judge "80 percent complete" differently, subcontractors have an incentive to round their own progress up, and nobody has a single, dated record of what a wall or a duct run looked like on a given day if a dispute over payment or defects comes up later.

How does it work?

  1. Capture the site. Workers walk their normal routes wearing a hardhat mounted camera, so the site is photographed at a set cadence without anyone doing an extra task.
  2. Build a digital twin. The images are stitched and located in the building, then matched automatically to the BIM model, element by element: which duct, partition, or fixture is visible, and whether it is there yet.
  3. Compare to the plan. The detected state of each element is compared with the schedule and the design, producing an objective percent complete per trade, per area and per task, plus a list of items that were meant to be installed and are not, or that do not match the design.
  4. Surface deviations. The system flags trades falling behind pace, sequencing conflicts (for example ceiling work starting before the ducts behind it are in), and installed work that differs from the BIM model.
  5. Act on it. Superintendents and project managers use the dashboard in the weekly trade meeting to compare each trade's measured pace of installed work against the schedule, and owners use it to verify progress claims behind payment applications instead of relying on self reported percentages. Keep the measurement at the level of the trade's output: using the same pace data to rank or discipline a named individual worker moves the system toward the Annex III employment category described under risk below.
Audience
Employee facing
Autonomy
Assist
Adoption
Early adopters
Channels
Internal tools

What is it worth?

Benchmarks are computed from the public deployments below: one data point per organization per KPI, with who made each claim.

Value benchmarks for AI for construction schedule and progress tracking
KPIMedianReported rangeData pointsClaimed by
Productivity gain70% vendor reported
66% to 95%
33 vendor
Error reductionToo few to pool
4.3% to 10%
22 vendor

Value drivers: Employee productivity, Speed and cycle time, Risk and loss reduction.

Indicative value

A general contractor running 10 active projects averaging 40,000 square feet each

USD 103,500 to USD 1.6 million

Superintendent and engineer time cost avoided on manual progress tracking per year

How this is calculated

Formula: projects * hoursPerProjectPerWeek * reductionShare * costPerHour * weeksPerYear. The low scenario uses every low input, the high scenario every high input.

InputLowHighBasis
Active projects tracked projects, projects515Editorial assumption for a mid size general contractor, replace with your own project count.
Superintendent and engineer hours spent on manual progress tracking, per project per week hoursPerProjectPerWeek, hours per project per week1530Doxel reports six superintendents and project engineers on one 82,000 square foot healthcare project spent a combined 60 hours a week on manual progress tracking before automation; scaled down to this reference project's average 40,000 square feet (60 times 40,000 divided by 82,000, about 29 hours, rounded to 30). Source
Share of manual tracking time removed reductionShare, fraction of tracking hours0.50.7Capped at NCC's reported 70% reduction in manual reporting time, the lower of the two reductions the evidence on this page reports; Doxel's higher reported 95% reduction at Layton Construction is not used, to keep the range conservative. Source
Fully loaded cost of a superintendent or project engineer hour costPerHour, USD per hour60100Editorial assumption, replace with your own fully loaded labor cost.
Weeks worked per year weeksPerYear, weeks4650Editorial assumption for an active construction calendar.

What it leaves out: Gross tracking labor cost avoided only. It leaves out the cost of the platform, the camera hardware, the one time BIM and schedule integration work, and any separate gains from fewer overbilling disputes or less rework, which the evidence on this page reports separately.

Market estimates (analyst estimates, not deployments)

Who already uses it?

9 public deployments, strongest evidence first. Grades: A regulator or audit, B the organization itself, C vendor case study, D anonymous or estimate.

Intel

United States · Manufacturing · 2026

ScaledGrade C

Intel uses Buildots to track progress and detect installation deviations on its multi fab semiconductor construction program, where a single fab has more than 50,000 activities. Buildots reports a 4.3 percent reduction in rework costs and about four weeks of delay avoided per fab. An Intel manager says the number of Intel users on the platform grew fivefold in 12 months and is in the hundreds.

  • Error reduction: 4.3%, per fab
    "This proactive approach contributed to a 4.3% reduction in rework costs and helped avoid approximately 4 weeks of delays per fab."
    Claimed by: vendor

JE Dunn Construction

United States · Real estate · 2026

ProductionGrade C

JE Dunn started with Buildots on a high rise residential project as a quality control tool and extended it to forecasting, trade partner communication and daily supervision. Buildots reports the platform has tracked more than 3 million square feet of JE Dunn construction across several projects. Its Delay Forecast tool compares actual progress with the schedule so project managers can move labor before a bottleneck hits. No percent or hour outcome is given.

No outcome disclosed.

Mace

United Kingdom · Real estate · 2026

ProductionGrade C

Mace used Buildots AI progress tracking on an extension of a large European airport with eight new gates and a project value of 500 million euros, replacing manual progress tracking. Automated reports showed when tasks started and finished, flagged activities falling behind and showed how small delays were adding up, and the team used the data in its trade meetings. Buildots headlines 4,200 work hours saved, while its results text describes a gap of 4,200 work hours that the reports exposed.

No outcome disclosed.

Multiplex

United Kingdom · Real estate · 2026

ProductionGrade C

Multiplex used Buildots AI at the 33 storey, 40,000 square meter One Leadenhall development in London. The platform forecast activities at risk of delay from actual against planned progress, replaced manual weekly reporting and flagged unfinished work, such as activities that stalled at about 90% completion, so site teams could settle open items before the next stage. Buildots describes fewer delays, less rework and better trade accountability but gives no measured outcome.

No outcome disclosed.

GTM Sud-Ouest TP GC

France · Real estate · 2025

ProductionGrade C

GTM Sud-Ouest TP GC, a subsidiary of VINCI Construction, and the general contractor SOCOTRAP used Buildots AI progress tracking on the 5,000 square meter fit out of an aerospace assembly line in Blagnac, near Toulouse. Delay forecasts, a progress dashboard in trade meetings and a photo explorer cut supervisors' site visits from at least six to two a day. Buildots reports the consortium's estimate that manual data collection time fell by about 66% over the six month project.

  • Productivity gain: about 66%, over the six month project, time spent on manual data collection
    "Over the six-month duration of the project, the team estimates that they reduced time spent on manual data collection by about 66%."
    Claimed by: vendor

Layton Construction

United States · Real estate · 2024

ProductionGrade C

Layton Construction, a US general contractor, used Doxel's AI progress tracking platform on an 82,000 square foot healthcare facility project. Before Doxel, six superintendents and project engineers spent a combined 60 hours a week manually tracking progress; Doxel cut that to 3 hours and reduced overbilling by 10 percent through precise progress tracking that eliminated disputes over the percent complete.

  • Productivity gain: 95%, On an 82,000 square foot healthcare facility project
    "On a recent 82,000 SqFt healthcare facility project, six superintendents and project engineers were initially spending a combined 60 hours per week manually tracking progress. With Doxel's technology, this time was slashed by 95%, reducing the task to just 3 hours total."
    Claimed by: vendor
  • Error reduction: 10%
    "Doxel enabled a 10% reduction in overbilling by providing precise progress tracking, simplifying billing processes, and eliminating disputes over the percent complete."
    Claimed by: vendor

Per Aarsleff A/S

Denmark · Real estate · 2024

ProductionGrade C

Per Aarsleff, which Buildots describes as Denmark's largest contractor, adopted Buildots' AI progress tracking for an 8,000 square metre, nine floor head office building in Aarhus. The contractor brought progress data into work planning meetings and trade handovers and used it to check subcontractor claims against installed work. Buildots reports that early detection identified scheduling conflicts that risked delaying the project by more than six weeks, and that acting on them avoided daily fines of 0.1% of the contract value.

No outcome disclosed.

NCC

Finland · Real estate · 2022

ProductionGrade C

NCC, one of the largest construction companies in the Nordic region, piloted Buildots' hardhat mounted camera and AI platform on Helsinki building projects, in a pilot announced in February 2022, to replace manual, subjective percent complete tracking with a measured comparison against its BIM model. The partnership expanded to four projects totaling 68,500 square metres, and Buildots reports large cuts in NCC's manual reporting time and more tasks completed on plan.

  • Productivity gain: 70%
    "70% reduction in manual reporting."
    Claimed by: vendor

Build Group

United States · Real estate · 2021

PilotGrade C

Build Group, a general contractor, used Buildots on the 19 story M2 residential tower in the 5M development in San Francisco, where two engineers walked the site with a hardhat mounted camera and the 360 degree captures were compared with a digital twin linked to the project's BIM models. Build Group was Buildots' first customer in the United States. Engineering News Record reported in August 2021 that the pilot went well enough for Build Group to plan the same approach on a 60 story mixed use tower in Seattle and a student housing project in San Francisco.

No outcome disclosed.

How do you implement it?

A model agnostic playbook: what to prepare, the order to build in, and what goes wrong.

Data you need

  • A BIM model broken into elements the AI can track against, kept reasonably current
  • A construction schedule with tasks the detected progress can be matched to
  • A fixed cadence of site photo capture, by staff wearing a hardhat mounted camera

Systems to integrate

  • BIM authoring or viewing platform (for example Autodesk Revit or Navisworks)
  • Scheduling tool (for example Primavera P6, Microsoft Project or the contractor's own tool)
  • Site capture hardware and its upload pipeline (hardhat mounted camera)
  • Document control or project management platform for routing flagged issues and RFIs

Complexity: Medium

Capturing images is simple once site staff have the hardhat mounted camera. Getting a BIM model that is actually kept current, mapping it cleanly to the schedule's tasks and agreeing with subcontractors that the automated percent complete is the number the weekly meeting and payment applications will use is where the effort goes.

  1. 1

    Start with one project and a clean BIM model

    Pick a project where the BIM model is actually kept up to date and the trades are willing to be measured, and agree up front which trades and floors are in scope for the pilot.

  2. 2

    Map the schedule to trackable elements

    Break the schedule's tasks down to the same level as the BIM elements the vision system detects (a duct run, a partition, a fixture), so a detected element maps to one task.

  3. 3

    Set the capture cadence and route

    Fix how often and by what route the site is captured, so every area gets covered on a predictable schedule and gaps in coverage do not look like missing progress.

  4. 4

    Put the dashboard in the weekly trade meeting

    Replace the subjective percent complete slide with the measured one, and agree with subcontractors in advance how disagreements between measured and self reported progress get resolved.

  5. 5

    Route deviations to an owner

    Send sequencing conflicts and design mismatches to the trade or engineer who owns the area, with the photo evidence attached, rather than only surfacing them on a dashboard nobody acts on.

  6. 6

    Extend to more projects once the workflow sticks

    Add projects once one team has changed how it runs its trade meetings around the data, not before, so the second project benefits from a working playbook rather than a repeated pilot.

Guardrails

  • Treat the automated percent complete as the primary number only after a defined period of running it alongside the manual estimate and reconciling differences
  • Keep a photo dated record of the evidence behind every reported percent complete, for payment application and dispute support
  • Mask or restrict access to imagery that incidentally captures workers, beyond what is needed to verify installed work
  • Require a human review before a flagged design mismatch is escalated to a stop work or rework instruction

KPIs to instrument

  • Time site staff spend on manual progress tracking, before and after
  • Share of tasks completed on the plan (Percent Plan Complete or equivalent), before and after
  • Overbilling or billing disputes tied to disagreements over percent complete
  • Coverage, meaning the share of the site captured on the agreed cadence, so gaps are visible

Human in the loop

Superintendents and project engineers decide what to do with a flagged deviation: the system measures and flags it, it does not instruct a trade to redo work or change the schedule. Owners and their quantity surveyors use the record as evidence, not as an automatic approval or rejection of a payment application.

Common failure modes

Stale BIM model
When the model is not kept current, the AI reports a mismatch that is really a documentation gap, not a site problem. Require model updates as part of the change process, not as an afterthought.
Capture gaps read as missing work
A missed walk or a blocked camera route can look like work has not started. Track and display capture coverage alongside the progress number.
Dashboard nobody acts on
Data with no owner and no place in the weekly meeting gets ignored. Assign an owner for every flagged deviation and review coverage and open flags every week.
Disputed percent complete undermines adoption
If subcontractors are not told in advance how the measured number will be used, a lower automated figure than their own estimate becomes a fight instead of a fix. Agree the reconciliation process before go live.

What are the risks and rules?

EU AI Act

Depends on design

Tracking built quantities against a BIM model and schedule is not itself an Annex III use.

Annex III point 4 covers employment, the management of workers and access to work as a self employed person, and brings a system into that category under point 4(b): AI used to make decisions affecting work related relationships, or, quoting the regulation, "to monitor and evaluate the performance and behavior of persons in such relationships", meaning employees, subcontracted individuals and others in a work related relationship with the organization.

Measuring the quantities and pace of the work itself, without naming or ranking a crew or an individual, stays out of that category. This page's own weekly meeting step (howItWorks, step 5) keeps the measurement at the level of the trade's output for exactly this reason: using the same per trade pace data to evaluate or discipline a named crew member or subcontracted individual would stretch the system into that high risk category.

Treat any such individual level use as high risk and apply the controls below to it, rather than relying on element level scoping alone.

Rules that apply

Controls to put in place

  • Written scope statement that the system measures installed work, not individual worker performance
  • Data retention and access limits on site imagery, since workers appear in it incidentally
  • Change control on the BIM to schedule mapping, since it decides what "on plan" means for a trade

Frequently asked questions

Does this replace the superintendent's judgment?

No. It replaces the manual estimate of percent complete with a measured one, and flags deviations for a human to act on. NCC's own account is that it freed time from arguing with subcontractors so staff could spend it actually fixing problems.

What has to be true before this works?

A BIM model that is reliably kept current, and a schedule broken down to the same level of detail as the elements the system tracks. Without both, the flagged mismatches mostly reflect a stale model, not a real site problem.

Is this only for the general contractor, or does the owner get value too?

The evidence on this page comes from contractor deployments: Doxel's Layton Construction case study reports a 10 percent reduction in overbilling, credited to precise progress tracking that eliminated disputes over the percent complete, and Buildots' NCC case study reports fewer conflicts that could have caused an overspend of tens of thousands of euros. Neither source says which party was overbilling or on which side an averted overspend would have landed. An owner still gets a related benefit from the same measured percent complete: this page's howItWorks step 5 describes owners using the dashboard to verify progress claims behind payment applications instead of relying on self reported percentages, though no evidence record on this page quantifies that owner side use.

Does it also check safety and quality, or only schedule progress?

Some platforms extend the same site imagery to installation quality checks against the BIM model as a byproduct, as NCC Finland reported. Treat that as a bonus of the same capture, not a substitute for a dedicated safety monitoring program.

How to cite this page

Blits.ai AI Use Case Library, "AI for construction schedule and progress tracking", last verified 29 September 2026, https://www.blits.ai/ai-use-cases/construction-schedule-and-progress-tracking. Licensed under CC BY 4.0. Method: how we verify use cases.

Changelog
  • 12 November 2026: Added deployments: GTM Sud-Ouest TP GC, Intel, JE Dunn Construction, Mace, Multiplex.
  • 12 November 2026: Quality check. The meta description now attributes both figures to the vendors that report them; removed the handling time reduction KPI (a per contact measure that does not fit site progress tracking); channel set to internal tools.
  • 13 October 2026: Added deployments: Build Group, Per Aarsleff A/S.
  • 30 September 2026: First published

Related use cases

Energy and utilities

AI analytics for smart meter and AMI data

Smart meter analytics is AI that turns readings from smart electricity, gas and water meters into usable information for utilities, instead of treating every meter and customer the same way. It monitors meter and network health at scale, estimates which appliances drive a household's usage from the meter signal alone, flags unusual consumption, and targets efficiency and electrification programs at the customers who will benefit most.

Deployments
5 public, best grade C
Reported satisfaction uplift
7%
Arizona Public Service (APS), vendor claim
Healthcare

AI command center for hospital bed and staff capacity planning

An AI command center for hospital bed and staff capacity planning predicts patient admissions, discharges and transfers, and helps a team of coordinators sequence bed assignments, staffing and moves. The coordinators sit in one room and act on real time predictions across a hospital or health system, so patients get into the right bed faster and existing capacity is used fully without adding beds.

Deployments
8 public, best grade B
Median cycle time reduction
36%
8 deployments
Retail and ecommerce

AI demand forecasting and automated replenishment for retail

Demand forecasting and replenishment is machine learning that forecasts demand for every item in every store or fulfillment center, day by day, and turns that forecast into automatic orders. It draws on sales history, promotions, prices, weather and local events, and places store and warehouse orders within limits set by planners, who handle the exceptions.

Deployments
10 public, best grade B
Reported food waste reduction
51%
Nemlig.com, vendor claim
Wealth and asset managementBanking

AI portfolio drift monitoring and rebalancing proposals

Portfolio drift monitoring and rebalancing is AI that continuously checks each client portfolio against its mandate or model and prepares a rebalancing proposal, for advisors and portfolio managers. It detects drift beyond agreed bands and prepares a tax aware, low turnover proposal with its rationale, which an advisor or portfolio manager approves before any trade is placed.

Deployments
3 public, best grade B
Autonomy
Copilot